Toronto District School Board
Skip to main content

George Peck Public School

Facility Condition Index

2022 -2023

The Facility Condition Index (FCI) rating is a measurement of the condition of a school building. It does not reflect on the safety of the building.

The health and safety of students, staff and community members are our top priority when planning school repairs. Our Facility Services staff works year-round to ensure our schools are safe regardless of their FCI rating.

Almost half of TDSB school buildings were built more than 60 years ago. Older schools often have a higher FCI rating as some building components such as walls, lights, floors and ventilation systems may require major repairs or replacement.


F.C.I.
52.70 %

Learn More

Learn more about the Renewal Needs Backlog and the Facility Condition Index, both of which include related Frequently Asked Questions.

Renewal Needs Backlog

The Toronto District School Board’s Renewal Needs Backlog (RNB) list identifies approximately 20,400 different repairs needed in our schools. The total value of those repairs was $4.2 billion as of March 2023.

For the 2022-2023 school year, the TDSB  received $292 million in provincial funding. These funds will be used to replace/repair building components identified during the Ministry’s school inspections, helping reduce the FCI of school buildings.

It is important to understand that these repairs do not represent a health or safety concern. Safety is a top priority for us at the TDSB and our maintenance plans are always focused on providing safe places for our students and staff. In order to do that, we fix the most critical problems related to health and safety first. Also, while components in a school building may be past their life expectancy (e.g. water boiler), they are in good condition and meet all required safety codes.

Legend

Urgent Building systems that are in critical condition and have surpassed their useful service life. These systems are very important to the operation of the building (e.g. boilers, other heat generating systems, fire alarm, sprinkler system, standpipe system, public address system, roofing, etc.). Although there is no specific timeframe to repair/replace these systems, it is recommended to do it as soon as funding becomes available.
High Building systems that are in critical or poor condition and their importance to the operation of the building is less than those classified as “urgent” (e.g. brick work, exterior doors, exterior windows, rooftop units, etc.). There is no specific timeframe to repair/replace these systems; however, repair/replacement is recommended as soon as funding becomes available.
Medium Building systems that are in fair condition with low importance to the operation of the building (e.g. floor finishes, washroom partitions, millwork, etc.).
Low Building systems that are in fair or good condition with very low importance to the operation of the building (e.g. wall partitions, interior wall finishes, interior doors, fences, etc.).
Brief DescriptionPriority
Auxiliary Equipment - HVAC Circulation Pumps RenewalUrgent
Heating Water Distribution Systems - Hydronic Piping RenewalUrgent
Branch Wiring - Original Building RenewalHigh
C302004 Floor Finishes - Vinyl Tile RenewalHigh
Ceiling Finishes - Fixed Acoustic Tile RenewalHigh
Controls & Instrumentation - BAS RenewalHigh
Controls and Instrumentation - Pneumatic RenewalHigh
Domestic Water Distribution - Electric Hot Water Heaters RenewalHigh
Domestic Water Distribution - Plumbing Piping RenewalHigh
Domestic Water Distribution - Sump Pumps and DHW Pump RenewalHigh
Exhaust Systems - Exhaust Fans RenewalHigh
Exterior Doors - Original Building RenewalHigh
G204001 Fencing and Gates - Chain Link Fence RenewalHigh
Interior Stair Construction - Original Building RenewalHigh
Lighting Equipment - Exterior Lighting RenewalHigh
Lighting and Branch Wiring - Exterior Lighting - Pole RenewalHigh
Lighting and Branch Wiring - Interior Lighting RenewalHigh
Perimeter Heating - Terminal Units RenewalHigh
Plumbing Fixtures - Bradley Basins RenewalHigh
Plumbing Fixtures - Lavatories RenewalHigh
Plumbing Fixtures - Urinals RenewalHigh
Plumbing Fixtures - Water Closets RenewalHigh
Plumbing Fixtures - Water Fountains RenewalHigh
Unit Ventilators RenewalHigh
Wall Finishes - PaintHigh
B203008 Exterior Doors - Hardware RenewalMedium
B308020 Exterior Soffits - Localized Deficiencies RenewalMedium
C1010 Partitions - Localized Deficiencies RenewalMedium
C102007 Interior Doors - Hardware RenewalMedium
C103001 Fittings - Washroom Partitions - Water Closet RenewalMedium
C103002 Fittings - Washroom Accessories RenewalMedium
Fittings - Millwork - Entire School RenewalMedium
G202003 Parking Lots - Paved - Asphalt RenewalMedium
G204072 Playing Fields - Asphalt School Playground RenewalMedium
Interior Doors - Original Building - Wood and Hollow Metal RenewalMedium
Roof Coverings - Section B RenewalMedium
Auxiliary Equipment - Chemical Feed System RenewalLow
Ceiling Finishes - Selected Classrooms RenewalLow
Exterior Doors - Automatic Device - Main Entrance RenewalLow
Exterior Doors - Original Building - Metal RenewalLow
Floor Finishes - Carpet RenewalLow
Floor Finishes - Gymnasium RenewalLow
Landscaping - General Areas RenewalLow
Playing Fields - Unpaved - Belair Playscape RenewalLow
Playing Fields - Unpaved - General Areas RenewalLow
Playing Fields - Unpaved - Jump Pits and Play Area RenewalLow
Signage - School & Traffic Movement RenewalLow